Home » Aptitude » Time and Work » Question
  1. A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
    1. 6 days
    2. 8 days
    3. 10 days
    4. 13 days
Correct Option: D

(A+B)’s 2 days’ work

= 2
1
+
1
=
10
121836

Remaining work
= 1 -
10
=
26
3636

Time taken by B to complete
26
part of work
36

=
26
× 18 = 13 days
36

Aliter : Using Rule 20,
Here, m = 12, n = 18, p = 2
Time taken by B
=
mn - p (m + n)
m

=
12 × 18 - 2(12 + 18)
12

=
216 - 60
= 13 days
12