  1. Match the items in Column I and their respective location in building/site in Column II, and select the appropriate option.










  1. View Hint View Answer Discuss in Forum

    Floor trap is also called as Nahni Trap (Nahni in hindi means washing/ bat hing place). I t is provided to prevent the foul gases by providing the water seal. To collect wastewater from the bathroom, wash area, wash basin, kitchen sinks etc.
    A gully trap is provided outside the building before connecting to external sewerage line and it collects waste water from the building.
    A bottle trap also called a waste trap, is an essential element of the wash-basin’s plumbing that keeps the bathroom hygienic and odor-free, as it prevents the foul gases from returning.
    Intercepting Trap is used at the Junction of house drain and sewer.

    Correct Option: C

    Floor trap is also called as Nahni Trap (Nahni in hindi means washing/ bat hing place). I t is provided to prevent the foul gases by providing the water seal. To collect wastewater from the bathroom, wash area, wash basin, kitchen sinks etc.
    A gully trap is provided outside the building before connecting to external sewerage line and it collects waste water from the building.
    A bottle trap also called a waste trap, is an essential element of the wash-basin’s plumbing that keeps the bathroom hygienic and odor-free, as it prevents the foul gases from returning.
    Intercepting Trap is used at the Junction of house drain and sewer.


  1. A colony of 50 people is served by a septic tank. The rate of water supply is 90lped in the colony and 40% of it is going to the septic tank. The retention period of the tank is 24 hours. The length of the septic tank is _____ meter (rounded off to two decimal places).
    Assume, storage capacity/person = 0.085 m3 (year)
    Space for digestion = 0.0425 m3 /person
    Depth of tank = 1.4 m ; Length : Width = 2 : 1









  1. View Hint View Answer Discuss in Forum

    Water in septic tank = 50 × 90 × 1 × 0.4 = 1.8 cu. m (40% of total consumption)
    Storage volume of septic tank = 0.085 × 50 = 4.25 cu. m
    Digestion volume of septic tank = 0.0425 × 50 = 2.125 cu. m
    Total volume = 1.8 + 4.25 + 2.125 = 8.175 cu. m

    Area of plane =
    Volume
    =
    8.175
    = 5.84 Sq m
    Height1.4

    If width is ‘a’, length will be ‘2a’
    2a2 = 5.84
    a = √(2.92) = 1.7
    Length of septic tank = 2a = 2 × 1.7 = 3.4 m

    Correct Option: B

    Water in septic tank = 50 × 90 × 1 × 0.4 = 1.8 cu. m (40% of total consumption)
    Storage volume of septic tank = 0.085 × 50 = 4.25 cu. m
    Digestion volume of septic tank = 0.0425 × 50 = 2.125 cu. m
    Total volume = 1.8 + 4.25 + 2.125 = 8.175 cu. m

    Area of plane =
    Volume
    =
    8.175
    = 5.84 Sq m
    Height1.4

    If width is ‘a’, length will be ‘2a’
    2a2 = 5.84
    a = √(2.92) = 1.7
    Length of septic tank = 2a = 2 × 1.7 = 3.4 m



  1. Solar panels are proposed to be installed on a building roof top to generate electricity. The size of each solar panel is 2 m2. The efficiency of each panel is 75%. The orientation of the solar panel and related solar data are given in the table below. As per above proposal ______ kWh solar power will be generated daily (rounded off to one decimal place).









  1. View Hint View Answer Discuss in Forum


    Solar power generated = Average solar radiation × Area × Average solar hours × Efficiency
    Solar power from the south orientation = 400 × 20 × 4 × 0.75 = 24 kWh
    Solar power from the West orientation = 300 × 10 × 2 × 0.75 = 4.5 kWh
    Total Solar power generated = 24 + 4.5 = 28.5 kWh

    Correct Option: A


    Solar power generated = Average solar radiation × Area × Average solar hours × Efficiency
    Solar power from the south orientation = 400 × 20 × 4 × 0.75 = 24 kWh
    Solar power from the West orientation = 300 × 10 × 2 × 0.75 = 4.5 kWh
    Total Solar power generated = 24 + 4.5 = 28.5 kWh


  1. A simply supported beam AB has a clear span of 7 meter. The bending moment diagram (BMD) of the beam due to a single concentrated load is shown in the figure below.

    The magnitude of the concentrated load in kN is _________.









  1. View Hint View Answer Discuss in Forum

    For eccentric point load on a simply supported beam

    Moment along any plane xx’,
    MX = RA x = Wbx / L
    MX = Wbx / L
    Maximum Bending Moment

    =
    Wab
    =
    (W × 3 × 4)
    L7

    36 =
    12W
    7

    W =
    (36 × 7)
    = 21
    12

    Correct Option: C

    For eccentric point load on a simply supported beam

    Moment along any plane xx’,
    MX = RA x = Wbx / L
    MX = Wbx / L
    Maximum Bending Moment

    =
    Wab
    =
    (W × 3 × 4)
    L7

    36 =
    12W
    7

    W =
    (36 × 7)
    = 21
    12



  1. Match the application in the field of construction in the Column I and the respective items in Column II and select appropriate option
    Column I Column II
    P. Polytetrafluoro-ethylene 1. Tendon (PTFE) membrane
    Q. Isolated compression component inside a network of continuous tensile member 2. TMT
    R. Cable used for pre-stressed concreting 3. Tensegrity
    S. Reinforcement bar used in RCC construction 4. TMD
    5. Teflon










  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: C