Power systems miscellaneous
- A 100 km long transmission line is loaded at 110 kV. If the loss of line is 5 MW and the load is 150 MVA, the resistance of the line is
-
View Hint View Answer Discuss in Forum
PL = I²LR
Here,I²L = 150 × 106 = 150 × 10³ 110 × 10³ 110 ∴ 15 × 106 = 150 ² × 106 × R 110
or R = 8.06 ohms/phaseCorrect Option: A
PL = I²LR
Here,I²L = 150 × 106 = 150 × 10³ 110 × 10³ 110 ∴ 15 × 106 = 150 ² × 106 × R 110
or R = 8.06 ohms/phase
- For a single phase overhead line having solid copper conductors of diameter 1 cm, spaced 60 cm between centers, the inductance in mH/km is
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- In a DC transmission line
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- In the above question, the maximum energy that could be produced daily is
-
View Hint View Answer Discuss in Forum
Load factor = Average demand Maximum demand
Average demand = 0.60 × 25 = 15 MW
Daily energy produced = Average demand × 24 = (15 × 24) = 360 MWhMaximum energy that could be produced = Actual energy produced in a day Plant use factor = 30 = 500 mwh/day 0.72 Correct Option: A
Load factor = Average demand Maximum demand
Average demand = 0.60 × 25 = 15 MW
Daily energy produced = Average demand × 24 = (15 × 24) = 360 MWhMaximum energy that could be produced = Actual energy produced in a day Plant use factor = 30 = 500 mwh/day 0.72
- A generating station has a maximum demand of 20 mW, load factor of 60%, a plant capacity factor of 50% and a plant use factor of 72%. What is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded?
-
View Hint View Answer Discuss in Forum
Load factor = Average demand Maximum demand or 0.60 = Average demand 25
∴ Average demand = 25 × 0.60 = 15 MWPlant capacity factor = Average demand Installed capacity or 0.50 = 15 Installed capacity ∴ Installed capacity = 15 = 30 MW 0.50
Reserve capacity of the plant = Installed capacity – Maximum demand = (30 – 25) = 5 MWCorrect Option: D
Load factor = Average demand Maximum demand or 0.60 = Average demand 25
∴ Average demand = 25 × 0.60 = 15 MWPlant capacity factor = Average demand Installed capacity or 0.50 = 15 Installed capacity ∴ Installed capacity = 15 = 30 MW 0.50
Reserve capacity of the plant = Installed capacity – Maximum demand = (30 – 25) = 5 MW