  1. A can finish a work in 7 days. B can finish the same work in 9 days. The number days required to finish the same work by both of them together is
    1. 1
      15
      16
    2. 2
      15
      16
    3. 3
      15
      16
    4. 4
      15
      16
Correct Option: C

A’s 1 day’s work =
1
7

B’s 1 day’s work =
1
9

∴ (A + B)’s 1 day’s work
=
1
+
1
79

=
1440
=
40
= 3
1
days
4681313

∴ Required time =
63
days
16

= 3
15
days
16