A can finish a work in 7 days. B can finish the same work in 9 days. The number days required to finish the same work by both of them together is
-
-
1 15 16 -
2 15 16 -
3 15 16 -
4 15 16
-
Correct Option: C
A’s 1 day’s work = | 7 |
B’s 1 day’s work = | 9 |
∴ (A + B)’s 1 day’s work
= | + | |||
7 | 9 |
= | = | = 3 | days | |||
468 | 13 | 13 |
∴ Required time = | days | 16 |
= 3 | days | 16 |