A can do a piece of work in 20 days and B in 15 days. With the help of C, they finish the work in 5 days. C can alone do the work in
-
- 5 days
- 6 days
- 10 days
- 12 days
Correct Option: D
A’s 1 day’s work = | |
20 |
B’s 1 day’s work = | |
15 |
(A + B + C)’s 1 day’s work = | |
5 |
∴ C’s 1 day’s work = | - | - | |||
5 | 20 | 15 |
= | = | = | |||
60 | 60 | 12 |
∴ Required time = 12 days