If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
-
-
4 4 days 5 - 4 days
-
3 4 days 5 - 6 days
-
Correct Option: A
A’s one day’s work = | 12 |
B’s one day’s work = | 8 |
(A + B)’s one day’s work
= | + | = | = | |||||
12 | 8 | 24 | 24 |
Now, | work is done in1day | 24 |
∴ 1 work is done in = | days | 5 |
= 4 | days | 5 |
Aliter : Using Rule 2,
Here, x = 12, y = 8
Required time taken
= | x + y |
= | = | |||
12 + 8 | 5 |
= 4 | days | 5 |