A can do 1/2 of a work in 9 days while B can do 1/3 of the same work in 6 days. How long would it take for A and B together to complete the work?
-
- 8 days
- 9 days
- 10 days
- 7 days
Correct Option: B
A’s 9 days’ work
= | 2 |
∴ A’s 1 day’s work
= | = | |||
2 × 9 | 18 |
B’s 6 days’ work = | 3 |
∴ B’s 1 day’s work
= | = | |||
3 × 6 | 18 |
∴ (A + B)’s 1 day’s work
= | + | = | = | |||||
18 | 18 | 18 | 9 |
∴ A and B both together will
complete the work in 9 days.
Aliter : Using Rule 2,
A’s 1 day work
= | = | days | ||
2 × 9 | 18 |
Required time taken
= | x + y |
= | 18 + 18 |
= | = 9 days | 36 |