  1. A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 2/5 th of the work is finished. How many additional men be employed so that the work may be completed on time, each man now working 9 hours a day?
    1. 35
    2. 40
    3. 45
    4. None of these
Correct Option: A


2
× 9 × x =
3
× 8 × 105
55

3 × 8 × 105
= 140
2 × 9

Number of additional men
= 140 – 105 = 35