Time and Work


  1. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days, In how many days will 20 women finish it?









  1. View Hint View Answer Discuss in Forum

    8M + 12W = 4 days (whole work)
    ⇒ 32M + 48W = 1 day ................ (1)
    Again 6M + 14W = 5 days
    ⇒ 30M + 70W = 1 day ................(2)

    Correct Option: A

    8M + 12W = 4 days (whole work)
    ⇒ 32M + 48W = 1 day ................ (1)
    Again 6M + 14W = 5 days
    ⇒ 30M + 70W = 1 day ................(2)
    From eq. (1) and (2)
    32M + 48W = 30M +70W
    ⇒ 2M = 22W
    ⇒ 1M = 11W
    Now, 30M + 70W = 1 day
    (30 X 11 X 70)W = 1 day
    Therefore 400W requires 1 day to complete the whole work.
    Thus 20W needs 20 days to complete the whole work.


  1. A and B can do a piece of work in 12 days, B and C can do it in 15 days and C and A can do the same work in 20 days. Find the number of days in which A alone can do the same job ?









  1. View Hint View Answer Discuss in Forum

    Work done by A and B in one day = 1/12
    Work done by B and C in one day = 1/15
    Work done by C and A is one day = 1/20

    On adding all these,
    2(A + B + C)'s work of one day = 1/12 + 1/15 +1/20 = 1/5
    ⇒ (A + B + C)'s one day work = 1/10
    ∴ A' s one day work = (A + B + C)'s one day work - (B + C )'s one day work

    Correct Option: B

    Work done by A and B in one day = 1/12
    Work done by B and C in one day = 1/15
    Work done by C and A is one day = 1/20

    On adding all these,
    2(A + B + C)'s work of one day = 1/12 + 1/15 +1/20 = 1/5
    ⇒ (A + B + C)'s one day work = 1/10
    ∴ A' s one day work = (A + B + C)'s one day work - (B + C )'s one day work
    ⇒ A's one day work 1/10 - 1/15 = 1/30
    Hence, A can do this work in 30 days.



  1. A leak in the bottom of a tank can empty the full tank in 6 h. An inlet pipe fills water at the rate of 4 L in a min. When the tank is full, the inlet is opened and due to the leak the tank is empty in 8 h. Find the capacity of the tank ?









  1. View Hint View Answer Discuss in Forum

    Efficiency of the leak = 1/6
    Combined efficiency of leak and inlet pipe
    So, efficiency of inlet pipe = 1/6 - 1/8 = (4 - 3)/24 = 1/24
    Inlet pipe can fill the tank in 24 h, at rate of 4 L/min.

    Correct Option: D

    Efficiency of the leak = 1/6
    Combined efficiency of leak and inlet pipe
    So, efficiency of inlet pipe = 1/6 - 1/8 = (4 - 3)/24 = 1/24
    Inlet pipe can fill the tank in 24 h, at rate of 4 L/min.
    ∴ Capacity = 24 x 60 x 4 = 5760 L


  1. A man, a women and a boy can do a job in 3, 4 and 12 days , respectively. How many boys must assist one man and one women to complete the job in one and a half days ?









  1. View Hint View Answer Discuss in Forum

    Portion of work completed by one man in 11/2 days.
    i.e., 3/2 days = 3/(2 x 3) = 1/2
    Portion of work completed by one women in 11/2 days.
    i.e., 3/2 days = 3/(2 x 4) = 3/8
    ∴ Portion of work completed by boys = 1 - (1/2 + 3/8) = 1/8
    Now, portion of work completed by each boy in 3/2 days = 3/(2 x 12) = 1/8

    Correct Option: D

    Portion of work completed by one man in 11/2 days.
    i.e., 3/2 days = 3/(2 x 3) = 1/2
    Portion of work completed by one women in 11/2 days.
    i.e., 3/2 days = 3/(2 x 4) = 3/8
    ∴ Portion of work completed by boys = 1 - (1/2 + 3/8) = 1/8
    Now, portion of work completed by each boy in 3/2 days = 3/(2 x 12) = 1/8
    Hence, only one boys would be required.



  1. Pipes A and B can fill a tank in 20 h and 30 h, respectively and pipe C can empty the full tank in 40 h. If all the pipes are opened together, how much time will be needed to make the tank full ?









  1. View Hint View Answer Discuss in Forum

    Net part filed in 1 h = (1/20 + 1/30 - 1/40) = 7/120

    Correct Option: B

    Net part filed in 1 h = (1/20 + 1/30 - 1/40) = 7/120
    Hence, the tank will be full in 120/7 = 171/7 h