  1. A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished?
    1. 10 days
    2. 9 days
    3. 12 days
    4. 14 days
Correct Option: C

Let the work be completed in x days.
According to the question,

x
+
x - 8
+
x - 6
= 1
163248

6x + 3x - 24 + 2x - 12
= 1
96

⇒ 11x – 36 = 96
⇒ 11x = 96 + 36 = 132
⇒ x =
132
= 12 days
11