A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
-
- 4 days
- 9 days
- 8 days
- 5 days
Correct Option: C
(A+B)’s 1 day’s work = | 15 |
(B+C)’s 1 day’s work = | 10 |
(A+C)’s 1 day’s work = | 12 |
On adding all three,
2(A+B+C)’s 1 day’s work
= | + | + | = | |||||
15 | 10 | 12 | 60 |
= | = | |||
60 | 4 |
∴ (A + B + C)’s 1 day’s work = | 8 |
∴ Required time = 8 days
Aliter : Using Rule 5,
Time taken = | xy + yz + zx |
= | 15 × 10 + 10 × 12 + 12 × 15 |
= | 150 + 120 + 180 |
= | = 8 days | 450 |