Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
-
- 40
- 48
- 32
- 30
Correct Option: B
(Ganesh + Ram + Sohan)’s 1 day’s work
= | 16 |
(Ganesh + Ram)’s 1 day’s work
= | 24 |
∴ Sohan’s 1 day’s work
= | - | = | = | |||||
16 | 24 | 48 | 48 |
∴ Required time = 48 days