A and B can do a piece of work in 72 days. B and C can do it in 120 days and A and C can do it in 90 days. A alone can do it in :
-
- 120 days
- 130 days
- 150 days
- 100 days
Correct Option: A
(A + B)’s 1 day’s work
= | ...........(i) | 72 |
(B + C)’s 1 day’s work
= | ...........(ii) | 120 |
(C + A)’s 1 day’s work
= | ...........(iii) | 90 |
On adding all three,
2 (A + B + C)’s 1 day’s work
= | + | + | ||||
72 | 120 | 90 |
= | = | = | ||||
360 | 360 | 30 |
∴ (A + B + C)’s 1 day’s work
= | ...........(iv) | 60 |
∴ A’s 1 day’s work
= Equation (iv) – (ii),
= | - | = | = | |||||
60 | 120 | 120 | 120 |
∴ Required time = 120 days