  1. A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?
    1. 42
      3
      days
      4
    2. 27
      1
      days
      7
    3. 17
      1
      days
      7
    4. 70 days
Correct Option: C

A’s 1 day’s work =
1
30

B’s 1 day’s work =
1
40

∴ (A + B)’s 1 day’s work
=
1
+
1
3040

=
4 + 3
=
7
120120

∴ Required time =
120
= 17
1
days
77