  1. A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
    1. 30 days
    2. 50 days
    3. 40 days
    4. 60 days
Correct Option: C

Let C alone complete the work in x days.
According to the question, A’s 7 days’ work + B’s 3 days’ work + C’s 2 days’ work = 1

7
+
3
+
2
= 1
1012x

2
= 1 -
7
-
1
x104

=
20 - 14 - 5
=
1
2020

⇒ x = 2 × 20 = 40 days