Home » Aptitude » Time and Work » Question
  1. If 8 men or 12 boys can do a piece of work in 16 days, the number of days required to complete the work by 20 men and 6 boys is
    1. 5
      1
      days
      3
    2. 6
      1
      days
      3
    3. 8
      1
      days
      3
    4. 7
      1
      days
      3
Correct Option: A

∵ 8 men ≡ 12 boys
∴ 4 men ≡ 6 boys
⇒ 20 men ≡ 30 boys
⇒ 20 men + 6 boys = 36 boys
∴ M1D1 = M2D2
⇒ 12 × 16 = 36 × D2

⇒ D2 =
12 × 16
=
16
= 5
1
days
3633

Aliter :
Using Rule 12,
Here, A = 8, B = 12, a = 16
A1 = 20, B1 = 6,
Required number of days =
a
=
16
A1
+
B1
20
+
6
AB812

=
16
=
16 × 2
= 5
1
days
5
+
1