  1. A can do a work in 5 days less than the time taken by B to do it. If both of them together take
    11
    1
    9

    days, then the time taken by ‘B’ alone to do the same work (in days) is
    1. 15
    2. 20
    3. 25
    4. 30
Correct Option: C

Using Rule 2,
If the time taken by B to complete the work be x days, then
time taken by A = (x – 5) days

1
+
1
=
9
xx - 5100

x - 5 + x
=
9
x(x - 5)100

⇒ 9x2 – 45x = 200x –500
⇒ 9x2 – 245x + 500 = 0
⇒ 9x2 – 225x – 20x + 500 = 0
⇒ 9x (x – 25) – 20 (x – 25) = 0
⇒ (x – 25) (9x – 20) = 0
⇒ x = 25 because x ≠
20
9