A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is
-
- 30 days
- 27 days
- 20 days
- 25 days
Correct Option: A
Using Rule 2,
Let time taken by B in completing the work = x days
∴ Time taken by A = (x – 10) days
∴ | + | = | ||||
x | x - 10 | 12 |
⇒ | = | |||
x(x - 10) | 12 |
⇒ 24x – 120 = x2 – 10x
⇒ x2 – 34x + 120 = 0
⇒ x2 – 30x – 4x + 120 = 0
⇒ x (x – 30) – 4 (x – 30) = 0
⇒ (x – 4) (x – 30) = 0
⇒ x = 30 because x ≠ 4