  1. A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only
    3
    1
    km road was completed.
    2

    Now how many more people were needed to finish the work in the specified time ?
    1. 480
    2. 80
    3. 200
    4. 100
Correct Option: C

Using Rule 1,
Remaining work

= 5 –
7
=
3
22

M1 × D1 × W2 = M2 × D2 × W1
⇒ 280 × 80 ×
3
2

= M2 × 20 ×
7
2

⇒ M2 =
280 × 80 × 3
= 480
20 × 7

∴ Required number of additional men = 480 – 280 = 200