-
A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work for 10 days when B and C leave.
How many days more will A take to complete the work?
-
- 16 days
- 15 days
- 18 days
- 20 days
Correct Option: C
Using Rule 3,
(A + B)’s 1 day’s work = | 30 |
(B + C)’s 1 day’s work = | 24 |
(C + A)’s 1 day’s work = | 20 |
Adding all the above, we have
2 ( A + B + C)’s 1 day’s work
= | + | + | ||||
30 | 24 | 20 |
= | = | = | ||||
120 | 120 | 8 |
∴ (A + B + C)’s 1 day’s work
= | = | |||
8 × 2 | 16 |
Now, all three worked together for 10 days.
∴ (A + B + C)’s 10 days’ work
= | × 10 = | |||
16 | 8 |
∴ Remaining part of work
= 1 - | = | = | ||||
8 | 8 | 8 |
Now, A’s 1 day’s work
= | - | = | = | |||||
16 | 24 | 48 | 48 |
Since, A finishes 1/48 part of work in 1 day
∴ A will finish 3/8 part of work in
1 × 48 × | = 18 days. | 8 |