  1. A, B and C individually can do a work in 10 days, 12 days and 15 days respectively. If they start working together, then the number of days required to finish the work is
    1. 16 days
    2. 8 days
    3. 4 days
    4. 2 days
Correct Option: C

Work done by A, B and C in 1 day =
1
+
1
+
1
101215

Work done by A, B and C in 1 day =
6 + 5 + 4
60

Work done by A, B and C in 1 day =
15
=
1
604

∴ Required time = 4 days
Second method to solve this question ,
Here , x = 10 , y = 12 , z = 15
Time Taken =
xyz
xy + yz + zx

Time Taken =
10 × 12 × 15
10 × 12 + 12 × 15 + 15 × 10

Time Taken =
1800
120 + 180 + 150

Time Taken =
1800
= 4 days
450