  1. A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
    1. 20 days
    2. 25 days
    3. 15 days
    4. 18 days
Correct Option: A

A’s 1 day’s work =
1
-
1
1230

A’s 1 day’s work =
5 - 2
60

A’s 1 day’s work =
3
=
1
6020

Hence, A alone will complete the work in 20 days.
Second method to solve this question ,
Here , x = 12 , y = 30
Time taken By A =
xy
x - y

Time taken By A =
12 × 30
30 - 12

Time taken By A =
12 × 30
= 20 days
18