  1. A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in ?
    1. 15 days
    2. 18 days
    3. 20 days
    4. 25 days
Correct Option: C

(A + B)'s 1 days work = 1/12
B's 1 days work = 1/30
∴ A's 1 days work = 1/12 - 1/30 = (5 - 2)/60 = 1/20
∴ A alone can finish the work in 20 days.