Home » Aptitude » Time and Work » Question
  1. A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
    1. 1/6
    2. 1/9
    3. 2/5
    4. 2/7
    5. 2/9
Correct Option: A

A's 1 day's work = 1/18
B's 1 day's work = 1/9
(A + B)'s 1 day's work = 1/9 + 1/18 = 3/18 = 1/6