Home » Aptitude » Time and Work » Question
  1. Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dilip together can complete the same work in 30 days, then how long will Shekhar take to complete it ?
    1. 60 days
    2. 62 days
    3. 40 days
    4. 56 days
Correct Option: A

∵ Work of (Ram + Dilip + Shekhar) for 1 day = 1/20
and work of (Ram + Dilip) for 1 day = 1/30
∴ Work of Shekhar for 1 day = 1 / 20 - 1 / 30 = 1/60
Hence, Shekhar will complete the work in 60 days.