  1. A and B separately can complete a work in 6 days and 3 days respectively. If they work together, then in how many days will they complete the work ?
    1. 4 days
    2. 3 days
    3. 2 days
    4. 5 days
Correct Option: C

Work completed by A + B in one day = 1/6 + 1/3 = 1/2
∴ Time taken by A + B to complete the work = 2 days.