Time and Work


  1. A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs 3000 as wages for the whole work, what are the daily wages of A, B and C respectively (in Rs ) ?









  1. View Hint View Answer Discuss in Forum

    A's 5 day work = 50%
    B's 5 day work = 33.33%
    C's 2 day work = 16.66% [100 - (50 + 33.33)]
    Ratio of contribution of work of A , B and C = 50 : 33.33 : 16.66 = 3 : 2 : 1
    A's total share = Rs. 1500
    B's total share = Rs. 1000
    C's total share = Rs. 500

    Correct Option: B

    A's 5 day work = 50%
    B's 5 day work = 33.33%
    C's 2 day work = 16.66% [100 - (50 + 33.33)]
    Ratio of contribution of work of A , B and C = 50 : 33.33 : 16.66 = 3 : 2 : 1
    A's total share = Rs. 1500
    B's total share = Rs. 1000
    C's total share = Rs. 500

    A's one day's earning = Rs. 300
    B's one day's earning = Rs. 200
    and C's one day's earning = Rs. 250


  1. Mr. Prashant has to build a wall 1000 meters long in 50 days. He employs 56 men but at the end of 27 days finds that only 448 meters are built. How many men must be employed so that the work may be finished in time?









  1. View Hint View Answer Discuss in Forum

    Fewer days, more men, more length, more men

    Correct Option: C

    Y = 56 x (27/23) x (552/448)
    =81

    Extra men required =81-56
    =25



  1. A and B can do a piece of work in 45 days and 40 days, respectively. They began to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days after which A left the work, is ?









  1. View Hint View Answer Discuss in Forum

    By the fundamental of work and time,
    x/45 + (x + 23) / 40 = 1

    Correct Option: C

    By the fundamental of work and time,
    x/45 + (x + 23)/40 = 1
    ⇒ x = 9 days


  1. A supplies 20 men who work for 8 h per days for 6 days. B supplies 15 men working at 9 h per day for 7 day and C supplies 10 men working 6 h per day for 8 days to do a certain lob. If ₹ 636 is paid for all the labour, what is C's share ?









  1. View Hint View Answer Discuss in Forum

    Total man hours work done by men supplied by A, B and C
    = (20 x 8 x 6), (15 x 9 x 7), (10 x 6 x 8) and the wages must be in the ratio of the work done.
    So, ₹ 636 has to divided among A, B and C in the ratio (20 x 8 x 6) : (15 x 9 x 7) : (10 x 6 x 8) = 64 : 63 : 32

    Correct Option: A

    Total man hours work done by men supplied by A, B and C
    = (20 x 8 x 6), (15 x 9 x 7), (10 x 6 x 8) and the wages must be in the ratio of the work done.
    So, ₹ 636 has to divided among A, B and C in the ratio (20 x 8 x 6) : (15 x 9 x 7) : (10 x 6 x 8) = 64 : 63 : 32
    ∴ C's share = (32/159) x 636 = ₹ 128



  1. A and B can complete a piece of work in 12 days while B and C in 15 days. A did the work for 3 days, B for 8 days and C for 10 days to complete the work. In how many days C alone can complete the work ?









  1. View Hint View Answer Discuss in Forum

    Fraction of work complete by (A and B) + Fraction of work complete by (B and C) + Fraction of work completed by C = 1
    As B did the work for 8 days we can say B did the work for 3 days with A and B did the work for 5 days with C. So, A and B together did the work for 3 days, B and C together did the work for 5 days, C alone did the work for 5 days.

    Correct Option: C

    Fraction of work complete by (A and B) + Fraction of work complete by (B and C) + Fraction of work completed by C = 1
    As B did the work for 8 days we can say B did the work for 3 days with A and B did the work for 5 days with C. So, A and B together did the work for 3 days, B and C together did the work for 5 days, C alone did the work for 5 days.
    ∴ 3/12 + 5/15 + 5/x = 1 or 5/x = 5/12
    i.e., x = 12 or C alone can complete the work in 12 days