- In the construction of networks, dummy activities are introduced in order to
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
If all activities other than S take the estimated amount of t i me, t he maxi mum dur at i on (in weeks) of the activity S without delaying the completion of the project is ______.
-
View Hint View Answer Discuss in Forum
Correct Option: A
- In PERT chart, the activity time distribution is
-
View Hint View Answer Discuss in Forum
Beta distribution extended to the Maximum & Minimum & gives strict definition for the mean & variance
Correct Option: D
Beta distribution extended to the Maximum & Minimum & gives strict definition for the mean & variance
- The standard deviation of the critical path is
-
View Hint View Answer Discuss in Forum
Variance = tp − tO 2 6 Total variance = 1 2 + 2 2 + 1 2 + 1 2 3 3 3 3 = 7 9
Standard deviation = √variance
⇒ √7/9 = 0.88Correct Option: C
Variance = tp − tO 2 6 Total variance = 1 2 + 2 2 + 1 2 + 1 2 3 3 3 3 = 7 9
Standard deviation = √variance
⇒ √7/9 = 0.88
- The critical path duration of the network (in days) is
-
View Hint View Answer Discuss in Forum
EST = Earliest start time
LFT = Latest Finish Time
∴ Path along which EST & LFT is equal are called critical path
Critical path duration is 18 days.Correct Option: D
EST = Earliest start time
LFT = Latest Finish Time
∴ Path along which EST & LFT is equal are called critical path
Critical path duration is 18 days.