  1. The critical path duration of the network (in days) is
    1. 11
    2. 14
    3. 17
    4. 18
Correct Option: D


EST = Earliest start time
LFT = Latest Finish Time
∴  Path along which EST & LFT is equal are called critical path
Critical path duration is 18 days.