Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. A component can be produced by any of the four processes I, II, III and IV. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of 100 pieces is









  1. View Hint View Answer Discuss in Forum

    TC = Fixed Cost + Variable cost
    TCI = 20 + 100 × 3 = Rs.320
    TCII = 50 + 100 × 1 = Rs.150
    TCIII = 40 + 100 × 2 = Rs.240
    TCIV = 10 + 100 × 4 = Rs.410
    Since total cost for the Process II is minimum
    So II is cost for economical point of view

    Correct Option: B

    TC = Fixed Cost + Variable cost
    TCI = 20 + 100 × 3 = Rs.320
    TCII = 50 + 100 × 1 = Rs.150
    TCIII = 40 + 100 × 2 = Rs.240
    TCIV = 10 + 100 × 4 = Rs.410
    Since total cost for the Process II is minimum
    So II is cost for economical point of view


  1. A linear programming problem is shown below:
    Maximise 3x + 7y
    Subjeot to 3x + 7y ≤ 10
    4x + 6y ≤ 8
    x, y ≥ 0









  1. View Hint View Answer Discuss in Forum

    z = 3x + 7y
    Constraints 3x + 7y ≤ 10
    4x + 6y < 8; x, y > 0
    Corresponding equations
    3x + 7y = 10; 4x + 6y = 8

    A (0, 4/3) z = 9.23
    B (2, 0) z = 6
    Thus, exactly one optimal solution.
    Hence, the correct option is (b).

    Correct Option: B

    z = 3x + 7y
    Constraints 3x + 7y ≤ 10
    4x + 6y < 8; x, y > 0
    Corresponding equations
    3x + 7y = 10; 4x + 6y = 8

    A (0, 4/3) z = 9.23
    B (2, 0) z = 6
    Thus, exactly one optimal solution.
    Hence, the correct option is (b).



  1. A manufacturer can produce 12000 bearings per day. The manufacturer received an order of 8000 bearings per day from a customer. The cost of holding a bearing in stock is Rs. 0.20 per month. Setup cost per production run is Rs. 500. Assuming 300 working days in a year, the frequency of production run should be









  1. View Hint View Answer Discuss in Forum

    D = 8000 × 300 bearings/year
    P = 12000 bearings/day
    C = 8000 bearings/day
    Ch = 0.12 × 12/year
    CO = 500/Production

    Q* = √
    2 × D × CO
    ×
    P
    ChP - C

    ⇒ √
    2 × 240000 × 500
    ×
    12000
    0.20 × 1212000 - 8000

    ⇒ 54772.526
    T =
    Q*
    C

    T ⇒ 6.84 days

    Correct Option: C

    D = 8000 × 300 bearings/year
    P = 12000 bearings/day
    C = 8000 bearings/day
    Ch = 0.12 × 12/year
    CO = 500/Production

    Q* = √
    2 × D × CO
    ×
    P
    ChP - C

    ⇒ √
    2 × 240000 × 500
    ×
    12000
    0.20 × 1212000 - 8000

    ⇒ 54772.526
    T =
    Q*
    C

    T ⇒ 6.84 days


  1. Consider the following data with reference to elementary deterministic economic order quantity model

    The total number of economic orders per year to meet the annual demand is _______.









  1. View Hint View Answer Discuss in Forum

    D = 100000
    C = 10 Rs
    Ch = 1.5
    CO = 30/order

    EOQ(Q*) = √
    2 × D × CO
    Ch

    = √
    2 × 100000 × 30
    = 2000 units
    1.5

    No of orders N* =
    D
    Q*

    N* =
    100000
    ⇒ 50
    2000

    Correct Option: B

    D = 100000
    C = 10 Rs
    Ch = 1.5
    CO = 30/order

    EOQ(Q*) = √
    2 × D × CO
    Ch

    = √
    2 × 100000 × 30
    = 2000 units
    1.5

    No of orders N* =
    D
    Q*

    N* =
    100000
    ⇒ 50
    2000



  1. A company uses 2555 units of an item annually. Delivery lead time is 8 days. The reorder point (in number of units) to achieve optimum inventory is









  1. View Hint View Answer Discuss in Forum

    Reorder level = LT × d + SS ↑If guessed
    Q ⇒ 2555 units
    Ls = 8 days
    Cycle Time = 365 days

    Q
    =
    n
    Tt

    t =
    Q
    t
    T

    t =
    2555 × 8
    = 56 units
    365

    Correct Option: C

    Reorder level = LT × d + SS ↑If guessed
    Q ⇒ 2555 units
    Ls = 8 days
    Cycle Time = 365 days

    Q
    =
    n
    Tt

    t =
    Q
    t
    T

    t =
    2555 × 8
    = 56 units
    365