  1. A company uses 2555 units of an item annually. Delivery lead time is 8 days. The reorder point (in number of units) to achieve optimum inventory is
    1. 7
    2. 8
    3. 56
    4. 60
Correct Option: C

Reorder level = LT × d + SS ↑If guessed
Q ⇒ 2555 units
Ls = 8 days
Cycle Time = 365 days

Q
=
n
Tt

t =
Q
t
T

t =
2555 × 8
= 56 units
365