Industrial Engineering Miscellaneous
- For a single server with Poisson arrival and exponential service time, the arrival rate is 12 per hour. Which one of the following service rates will provide a steady state finite queue length?
-
View Hint View Answer Discuss in Forum
For steady state, μ > λ
as λ = 12 customers/hour, we need to select option (d)Correct Option: D
For steady state, μ > λ
as λ = 12 customers/hour, we need to select option (d)
- In a single-channel queuing model, the customer arrival rate is 12 per hour and the serving rate is 24 per hour. The expected time that a customer is in queue is minutes.
-
View Hint View Answer Discuss in Forum
λ = 12 /hr, μ = 24 /hr
ρ = λ = 12 = 0.5 μ 24
Expected time that the customer in the queueWq = Lq = Ls - ρ λ λ = ρ - ρ = 0.5 - 0.5 1 - ρ 1 - 0.5 λ 12 = 0.5 hr = 0.5 × 60 min 12 12
= 2.5 minCorrect Option: B
λ = 12 /hr, μ = 24 /hr
ρ = λ = 12 = 0.5 μ 24
Expected time that the customer in the queueWq = Lq = Ls - ρ λ λ = ρ - ρ = 0.5 - 0.5 1 - ρ 1 - 0.5 λ 12 = 0.5 hr = 0.5 × 60 min 12 12
= 2.5 min
- Which one of the following is NOT a decision taken during the aggregate production planning stage?
-
View Hint View Answer Discuss in Forum
NA
Correct Option: B
NA
- The Product structure of an assembly P is shown in the figure.
Estimated demand for end product P is as follows:
Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is
-
View Hint View Answer Discuss in Forum
The M.R.P. for R is given by
If 6P – 12800 ≥ 0 then the capacity is feasible
∴ Minimization, 6P = 12800
⇒ P ≅ 2200Correct Option: C
The M.R.P. for R is given by
If 6P – 12800 ≥ 0 then the capacity is feasible
∴ Minimization, 6P = 12800
⇒ P ≅ 2200
- Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project
The critical path (CP) in the network is
-
View Hint View Answer Discuss in Forum
Critical path ⇒ 1 – 4 – 3 – 5
Time takes = 8 daysCorrect Option: B
Critical path ⇒ 1 – 4 – 3 – 5
Time takes = 8 days