Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. For a single server with Poisson arrival and exponential service time, the arrival rate is 12 per hour. Which one of the following service rates will provide a steady state finite queue length?









  1. View Hint View Answer Discuss in Forum

    For steady state, μ > λ
    as λ = 12 customers/hour, we need to select option (d)

    Correct Option: D

    For steady state, μ > λ
    as λ = 12 customers/hour, we need to select option (d)


  1. In a single-channel queuing model, the customer arrival rate is 12 per hour and the serving rate is 24 per hour. The expected time that a customer is in queue is minutes.









  1. View Hint View Answer Discuss in Forum

    λ = 12 /hr, μ = 24 /hr

    ρ =
    λ
    =
    12
    = 0.5
    μ24

    Expected time that the customer in the queue
    Wq =
    Lq
    =
    Ls - ρ
    λλ

    =  
    ρ
    - ρ =  
    0.5
    - 0.5
    1 - ρ
    1 - 0.5
    λ12

    =
    0.5
    hr =
    0.5
    × 60 min
    1212

    = 2.5 min

    Correct Option: B

    λ = 12 /hr, μ = 24 /hr

    ρ =
    λ
    =
    12
    = 0.5
    μ24

    Expected time that the customer in the queue
    Wq =
    Lq
    =
    Ls - ρ
    λλ

    =  
    ρ
    - ρ =  
    0.5
    - 0.5
    1 - ρ
    1 - 0.5
    λ12

    =
    0.5
    hr =
    0.5
    × 60 min
    1212

    = 2.5 min



  1. Which one of the following is NOT a decision taken during the aggregate production planning stage?









  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: B

    NA


  1. The Product structure of an assembly P is shown in the figure.

    Estimated demand for end product P is as follows:

    Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is









  1. View Hint View Answer Discuss in Forum

    The M.R.P. for R is given by

    If 6P – 12800 ≥ 0 then the capacity is feasible
    ∴ Minimization, 6P = 12800
    ⇒ P ≅ 2200

    Correct Option: C

    The M.R.P. for R is given by

    If 6P – 12800 ≥ 0 then the capacity is feasible
    ∴ Minimization, 6P = 12800
    ⇒ P ≅ 2200



  1. Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project

    The critical path (CP) in the network is









  1. View Hint View Answer Discuss in Forum


    Critical path ⇒ 1 – 4 – 3 – 5
    Time takes = 8 days

    Correct Option: B


    Critical path ⇒ 1 – 4 – 3 – 5
    Time takes = 8 days