  1. Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project

    The critical path (CP) in the network is
    1. 1-2-3-5
    2. 1-4-3-5
    3. 1-2-3-4-5
    4. 1-4-5
Correct Option: B


Critical path ⇒ 1 – 4 – 3 – 5
Time takes = 8 days