  1. The Product structure of an assembly P is shown in the figure.

    Estimated demand for end product P is as follows:

    Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is
    1. 1000
    2. 1200
    3. 2200
    4. 2400
Correct Option: C

The M.R.P. for R is given by

If 6P – 12800 ≥ 0 then the capacity is feasible
∴ Minimization, 6P = 12800
⇒ P ≅ 2200