Industrial Engineering Miscellaneous
- A project has four activities P, O, H and S as shown below.
The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is_________ .
-
View Hint View Answer Discuss in Forum
Critical path ⇒ 1 – 2 – 3 – 4
⇒ 5 + 4 + 1 + 2 = 12 days
For 12 days :-
10,000 + 12 (200) = 12400
For 9 days :-
= 10,000 + 9 (200) + (400 + 300)
= 12,500Correct Option: C
Critical path ⇒ 1 – 2 – 3 – 4
⇒ 5 + 4 + 1 + 2 = 12 days
For 12 days :-
10,000 + 12 (200) = 12400
For 9 days :-
= 10,000 + 9 (200) + (400 + 300)
= 12,500
- If duration of activity f is changed to 10 days, then the critical path for the project is
-
View Hint View Answer Discuss in Forum
If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.
Correct Option: A
If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.
- For the linear programming problem:
Maximize z = 3x1 + 2x2
Subject to –2x1 + 3x2 ≤ 9
x1 – 5x2 ≥ – 20
x1, x2 ≥ 0
The above problem has
-
View Hint View Answer Discuss in Forum
Maximize Z = 3X1 + 2X2
Subject to
– 2X1 + 3X2 ≤ 9
X1 – 5X2 ≥ 20
X1, X2 ≥ 0Correct Option: C
Maximize Z = 3X1 + 2X2
Subject to
– 2X1 + 3X2 ≤ 9
X1 – 5X2 ≥ 20
X1, X2 ≥ 0
- Consider an objective function Z(x1, x2) = 3x1 + 9x2 and the constraints
x1 + x2 ≤ 8
x1 + 2x2 ≤ 4
x1 ≥ 0, x2 ≥ 0
The maximum value of the objective function is __________.
-
View Hint View Answer Discuss in Forum
Z = 3x1 + 4x2
x1 + x2 ≤ 8
x1 + 2x1 ≤ 4
x1, x1 ≥ 0
At point A:
z = 3 (4) +9 (0) = 12
At point B:
z = 3 (0) + 9 (2) = 18Correct Option: B
Z = 3x1 + 4x2
x1 + x2 ≤ 8
x1 + 2x1 ≤ 4
x1, x1 ≥ 0
At point A:
z = 3 (4) +9 (0) = 12
At point B:
z = 3 (0) + 9 (2) = 18
- A linear programming problem is shown below:
Maximise 3x + 7y
Subjeot to 3x + 7y ≤ 10
4x + 6y ≤ 8
x, y ≥ 0
-
View Hint View Answer Discuss in Forum
z = 3x + 7y
Constraints 3x + 7y ≤ 10
4x + 6y < 8; x, y > 0
Corresponding equations
3x + 7y = 10; 4x + 6y = 8
A (0, 4/3) z = 9.23
B (2, 0) z = 6
Thus, exactly one optimal solution.
Hence, the correct option is (b).Correct Option: B
z = 3x + 7y
Constraints 3x + 7y ≤ 10
4x + 6y < 8; x, y > 0
Corresponding equations
3x + 7y = 10; 4x + 6y = 8
A (0, 4/3) z = 9.23
B (2, 0) z = 6
Thus, exactly one optimal solution.
Hence, the correct option is (b).