Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. A project has four activities P, O, H and S as shown below.

    The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is_________ .









  1. View Hint View Answer Discuss in Forum


    Critical path ⇒ 1 – 2 – 3 – 4
    ⇒ 5 + 4 + 1 + 2 = 12 days
    For 12 days :-
    10,000 + 12 (200) = 12400
    For 9 days :-
    = 10,000 + 9 (200) + (400 + 300)
    = 12,500

    Correct Option: C


    Critical path ⇒ 1 – 2 – 3 – 4
    ⇒ 5 + 4 + 1 + 2 = 12 days
    For 12 days :-
    10,000 + 12 (200) = 12400
    For 9 days :-
    = 10,000 + 9 (200) + (400 + 300)
    = 12,500


  1. If duration of activity f is changed to 10 days, then the critical path for the project is









  1. View Hint View Answer Discuss in Forum

    If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.

    Correct Option: A

    If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.



  1. For the linear programming problem:
    Maximize z = 3x1 + 2x2
    Subject to –2x1 + 3x2 ≤ 9
    x1 – 5x2 ≥ – 20
    x1, x2 ≥ 0
    The above problem has









  1. View Hint View Answer Discuss in Forum

    Maximize Z = 3X1 + 2X2
    Subject to
    – 2X1 + 3X2 ≤ 9
    X1 – 5X2 ≥ 20
    X1, X2 ≥ 0

    Correct Option: C

    Maximize Z = 3X1 + 2X2
    Subject to
    – 2X1 + 3X2 ≤ 9
    X1 – 5X2 ≥ 20
    X1, X2 ≥ 0


  1. Consider an objective function Z(x1, x2) = 3x1 + 9x2 and the constraints
    x1 + x2 ≤ 8
    x1 + 2x2 ≤ 4
    x1 ≥ 0, x2 ≥ 0
    The maximum value of the objective function is __________.









  1. View Hint View Answer Discuss in Forum

    Z = 3x1 + 4x2
    x1 + x2 ≤ 8
    x1 + 2x1 ≤ 4
    x1, x1 ≥ 0

    At point A:
    z = 3 (4) +9 (0) = 12
    At point B:
    z = 3 (0) + 9 (2) = 18

    Correct Option: B

    Z = 3x1 + 4x2
    x1 + x2 ≤ 8
    x1 + 2x1 ≤ 4
    x1, x1 ≥ 0

    At point A:
    z = 3 (4) +9 (0) = 12
    At point B:
    z = 3 (0) + 9 (2) = 18



  1. A linear programming problem is shown below:
    Maximise 3x + 7y
    Subjeot to 3x + 7y ≤ 10
    4x + 6y ≤ 8
    x, y ≥ 0









  1. View Hint View Answer Discuss in Forum

    z = 3x + 7y
    Constraints 3x + 7y ≤ 10
    4x + 6y < 8; x, y > 0
    Corresponding equations
    3x + 7y = 10; 4x + 6y = 8

    A (0, 4/3) z = 9.23
    B (2, 0) z = 6
    Thus, exactly one optimal solution.
    Hence, the correct option is (b).

    Correct Option: B

    z = 3x + 7y
    Constraints 3x + 7y ≤ 10
    4x + 6y < 8; x, y > 0
    Corresponding equations
    3x + 7y = 10; 4x + 6y = 8

    A (0, 4/3) z = 9.23
    B (2, 0) z = 6
    Thus, exactly one optimal solution.
    Hence, the correct option is (b).