If duration of activity f is changed to 10 days, then the critical path for the project is
-
- Critical path remains the same and the total duration to complete the project changes to 19 days.
- Critical path and the total duration to complete the project remains the same.
- Critical path changes but the total duration tocomplete the project remains the same.
- Critical path changes and the total duration to complete the project changes to 17 days.
Correct Option: A
If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.