A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
If all activities other than S take the estimated amount of t i me, t he maxi mum dur at i on (in weeks) of the activity S without delaying the completion of the project is ______.
-
- 2
- 9
- 13
- 8