Industrial Engineering Miscellaneous
- In PERT analysis a critical activity has
-
View Hint View Answer Discuss in Forum
Earliest Start = Least Start = 0 Float Correct Option: B
Earliest Start = Least Start = 0 Float
- A dummy activity is used in PERT network to describe
-
View Hint View Answer Discuss in Forum
Dummy activities often have a zero completion time & are used to represents precendence relationship.
Correct Option: A
Dummy activities often have a zero completion time & are used to represents precendence relationship.
- In PERT, the distribution of activity times is assumed to be
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- A company produces two types of toys: P and Q. Production time of Q is twice that of P and the company has a maximum of 2000 time units per day. The supply of raw material is just sufficient to produce 1500 toys (of any type) per day. Toy type Q requires an electric switch which is available @ 600 pieces per day only. The company makes a profit of Rs. 3 and Rs. 5 on type P and Q respectively. For maximization of profits, the daily production quantities of P and Q toys should respectively be
-
View Hint View Answer Discuss in Forum
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 unitsCorrect Option: A
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 units
- A manufacturer produces two types of products, 1 and 2, at production levels of x1 and x2 respectively. The profit is given is 2x1 + 5x2. The production constraints are :
x1 + 3x2 < 40
3x1 + x2 < 24
x1 + x2 < 10
x1 > 0 , x2 > 0
The maximum profit which can meet the constraints is
-
View Hint View Answer Discuss in Forum
Feasible Region (0– A – B – C– 0)
At point (A) 0, 10)
Z = 2 (0) + 5 (10) = 50
At point B (7,3)
Z = 2(7) + 5(3) = 2y
At point C (8, 0)
Z = 2(16) + 5(0) = (16) 2
⇒ 32
Hence maximum profit is Zmax = 50
No correct option is given.Correct Option: C
Feasible Region (0– A – B – C– 0)
At point (A) 0, 10)
Z = 2 (0) + 5 (10) = 50
At point B (7,3)
Z = 2(7) + 5(3) = 2y
At point C (8, 0)
Z = 2(16) + 5(0) = (16) 2
⇒ 32
Hence maximum profit is Zmax = 50
No correct option is given.