Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. The sale of cycles in a shop in four consecutive months are given as 70, 68, 82, 95. Exponentially smoothing average method with a smoothing factor of 0.4 is used in forecasting. The expected number of sales in the next month is









  1. View Hint View Answer Discuss in Forum

    Ft+1 = Dt + α(1 – α) Dt–1 + α(1 – α) ² Dt–2
    Ft+1 = 0.4 (95) + 0.4 (1 – 0.4)² + α(1 – α)³ Dt–3 + (0.4) (1 – 0.4)² × 68 + (0.4) (1 – 0.4)³ × 70
    Ft–1 = 73.52 units

    Correct Option: C

    Ft+1 = Dt + α(1 – α) Dt–1 + α(1 – α) ² Dt–2
    Ft+1 = 0.4 (95) + 0.4 (1 – 0.4)² + α(1 – α)³ Dt–3 + (0.4) (1 – 0.4)² × 68 + (0.4) (1 – 0.4)³ × 70
    Ft–1 = 73.52 units


  1. A regression model is used to express a variable V as a function of another variable X, this implies that









  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: A

    NA



  1. In an assembly line for assembling toys, five workers are assigned tasks which take times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is









  1. View Hint View Answer Discuss in Forum

    Assuming cycle time = 10 + 8 + 6 + 9 + 10 = 43

    Balance delay = 1 -
    ∑ ti
    = 1-
    43
    = 0.14
    n × te5 × 10

    = 14%

    Correct Option: C

    Assuming cycle time = 10 + 8 + 6 + 9 + 10 = 43

    Balance delay = 1 -
    ∑ ti
    = 1-
    43
    = 0.14
    n × te5 × 10

    = 14%


  1. If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that









  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: C

    NA



  1. A manufacturer produces two types of products, 1 and 2, at production levels of x1 and x2 respectively. The profit is given is 2x1 + 5x2. The production constraints are :
    x1 + 3x2 < 40
    3x1 + x2 < 24
    x1 + x2 < 10
    x1 > 0 , x2 > 0
    The maximum profit which can meet the constraints is









  1. View Hint View Answer Discuss in Forum


    Feasible Region (0– A – B – C– 0)
    At point (A) 0, 10)
    Z = 2 (0) + 5 (10) = 50
    At point B (7,3)
    Z = 2(7) + 5(3) = 2y
    At point C (8, 0)
    Z = 2(16) + 5(0) = (16) 2
    ⇒ 32
    Hence maximum profit is Zmax = 50
    No correct option is given.

    Correct Option: C


    Feasible Region (0– A – B – C– 0)
    At point (A) 0, 10)
    Z = 2 (0) + 5 (10) = 50
    At point B (7,3)
    Z = 2(7) + 5(3) = 2y
    At point C (8, 0)
    Z = 2(16) + 5(0) = (16) 2
    ⇒ 32
    Hence maximum profit is Zmax = 50
    No correct option is given.