Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. A company produces two types of toys: P and Q. Production time of Q is twice that of P and the company has a maximum of 2000 time units per day. The supply of raw material is just sufficient to produce 1500 toys (of any type) per day. Toy type Q requires an electric switch which is available @ 600 pieces per day only. The company makes a profit of Rs. 3 and Rs. 5 on type P and Q respectively. For maximization of profits, the daily production quantities of P and Q toys should respectively be









  1. View Hint View Answer Discuss in Forum

    Zmax = 3P + 5Q
    subject to P + 2Q ≤ 2000
    P + Q ≤ 1500
    Q ≤ 600
    P, Q ≥ 0

    Feasible solution (O A B C D)
    Since At point A (1500,0)
    Z = 3 × 1500 + 5 × 0 = 4500
    At Point B (1000, 500)
    Z = 3 × 1000 + 5 × 500 = 5500
    At point C (800, 600)
    Z = 3 × 800 + 5 × 600 = 5400
    At Point O (0, 600)
    Z = 3 × 0 + 5 × 600 = 3000
    Hence Z in maximum at B (1000,500)
    P = 1000 units and Q = 500 units

    Correct Option: A

    Zmax = 3P + 5Q
    subject to P + 2Q ≤ 2000
    P + Q ≤ 1500
    Q ≤ 600
    P, Q ≥ 0

    Feasible solution (O A B C D)
    Since At point A (1500,0)
    Z = 3 × 1500 + 5 × 0 = 4500
    At Point B (1000, 500)
    Z = 3 × 1000 + 5 × 500 = 5500
    At point C (800, 600)
    Z = 3 × 800 + 5 × 600 = 5400
    At Point O (0, 600)
    Z = 3 × 0 + 5 × 600 = 3000
    Hence Z in maximum at B (1000,500)
    P = 1000 units and Q = 500 units


  1. In PERT, the distribution of activity times is assumed to be









  1. View Hint View Answer Discuss in Forum

    NA

    Correct Option: C

    NA



  1. A dummy activity is used in PERT network to describe









  1. View Hint View Answer Discuss in Forum

    Dummy activities often have a zero completion time & are used to represents precendence relationship.

    Correct Option: A

    Dummy activities often have a zero completion time & are used to represents precendence relationship.


  1. Production flow analysis (PFA) is a method of identifying part families that uses data from









  1. View Hint View Answer Discuss in Forum

    Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.

    Correct Option: D

    Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.



  1. On an average 100 customers arrive at a place each hour, and on the average the server can process 120 customers per hour. What is the proportion of time the server is idle?.









  1. View Hint View Answer Discuss in Forum

    The proportion of time the server is idle = 1 - ρ

    Correct Option: A

    The proportion of time the server is idle = 1 - ρ