Industrial Engineering Miscellaneous
- A company produces two types of toys: P and Q. Production time of Q is twice that of P and the company has a maximum of 2000 time units per day. The supply of raw material is just sufficient to produce 1500 toys (of any type) per day. Toy type Q requires an electric switch which is available @ 600 pieces per day only. The company makes a profit of Rs. 3 and Rs. 5 on type P and Q respectively. For maximization of profits, the daily production quantities of P and Q toys should respectively be
-
View Hint View Answer Discuss in Forum
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 unitsCorrect Option: A
Zmax = 3P + 5Q
subject to P + 2Q ≤ 2000
P + Q ≤ 1500
Q ≤ 600
P, Q ≥ 0
Feasible solution (O A B C D)
Since At point A (1500,0)
Z = 3 × 1500 + 5 × 0 = 4500
At Point B (1000, 500)
Z = 3 × 1000 + 5 × 500 = 5500
At point C (800, 600)
Z = 3 × 800 + 5 × 600 = 5400
At Point O (0, 600)
Z = 3 × 0 + 5 × 600 = 3000
Hence Z in maximum at B (1000,500)
P = 1000 units and Q = 500 units
- In PERT, the distribution of activity times is assumed to be
-
View Hint View Answer Discuss in Forum
NA
Correct Option: C
NA
- A dummy activity is used in PERT network to describe
-
View Hint View Answer Discuss in Forum
Dummy activities often have a zero completion time & are used to represents precendence relationship.
Correct Option: A
Dummy activities often have a zero completion time & are used to represents precendence relationship.
- Production flow analysis (PFA) is a method of identifying part families that uses data from
-
View Hint View Answer Discuss in Forum
Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.
Correct Option: D
Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.
- On an average 100 customers arrive at a place each hour, and on the average the server can process 120 customers per hour. What is the proportion of time the server is idle?.
-
View Hint View Answer Discuss in Forum
The proportion of time the server is idle = 1 - ρ
Correct Option: A
The proportion of time the server is idle = 1 - ρ