Industrial Engineering Miscellaneous
- Production flow analysis (PFA) is a method of identifying part families that uses data from
-
View Hint View Answer Discuss in Forum
Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.
Correct Option: D
Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.
- On an average 100 customers arrive at a place each hour, and on the average the server can process 120 customers per hour. What is the proportion of time the server is idle?.
-
View Hint View Answer Discuss in Forum
The proportion of time the server is idle = 1 - ρ
Correct Option: A
The proportion of time the server is idle = 1 - ρ
- In a single server infinite population queuing model. Arrivals follow a Poisson distribution with mean λ = 4 per hour. The service times are exponential with mean service time equal to 12 minutes. The expected length of the queue will be
-
View Hint View Answer Discuss in Forum
λ = 4 , μ = 1 60 12 ∴ ρ = λ = 48 = 0.8 μ 60 Wq = queue length = ρ2 = (0.8)2 = 3.2 (1 – ρ) (1 – 0.8)
Correct Option: B
λ = 4 , μ = 1 60 12 ∴ ρ = λ = 48 = 0.8 μ 60 Wq = queue length = ρ2 = (0.8)2 = 3.2 (1 – ρ) (1 – 0.8)
- In a time series forecasting model, the demand for five time periods was 10,13,15,18 and 22. A linear regression fit resulted in an equation F = 6.9 + 2.9 where F is the forecast for period f. The sum of absolute deviations for the five data is
-
View Hint View Answer Discuss in Forum
F = 6.9 + 2.9 t
F1 = 6.9 + 2.9 × 1 ⇒ 9.8
F2 = 6.9 + 2.9 × 2 ⇒ 12.7
F3 = 6.9 + 2.9 × 3 ⇒ 15.6
F4 = 6.9 + 2.9 × 4 ⇒ 18.5
F5 = 6.9 + 2.9 × 5 = 21.4
D1 = 10 D2 = 13 03 = 15
D4 = 16 D5 = 22
SAD = ∑ |ei|
SAD = |10 − 9.8| + |13 − 12.7| + |15 − 15.6| + |18 − 18.5| + |22 − 21.4 |
Absolute Deviation = 2.2Correct Option: A
F = 6.9 + 2.9 t
F1 = 6.9 + 2.9 × 1 ⇒ 9.8
F2 = 6.9 + 2.9 × 2 ⇒ 12.7
F3 = 6.9 + 2.9 × 3 ⇒ 15.6
F4 = 6.9 + 2.9 × 4 ⇒ 18.5
F5 = 6.9 + 2.9 × 5 = 21.4
D1 = 10 D2 = 13 03 = 15
D4 = 16 D5 = 22
SAD = ∑ |ei|
SAD = |10 − 9.8| + |13 − 12.7| + |15 − 15.6| + |18 − 18.5| + |22 − 21.4 |
Absolute Deviation = 2.2
- The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
-
View Hint View Answer Discuss in Forum
Way to locate machine at four plans
4! = 24Correct Option: D
Way to locate machine at four plans
4! = 24