Industrial Engineering Miscellaneous


Industrial Engineering Miscellaneous

Industrial Engineering

  1. Production flow analysis (PFA) is a method of identifying part families that uses data from









  1. View Hint View Answer Discuss in Forum

    Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.

    Correct Option: D

    Production flow analysis (PFA) is a comprehensive method for material analysis part family formations, design of manufacturing cell & facility layout design. These operation are taken from the Route sheet.


  1. On an average 100 customers arrive at a place each hour, and on the average the server can process 120 customers per hour. What is the proportion of time the server is idle?.









  1. View Hint View Answer Discuss in Forum

    The proportion of time the server is idle = 1 - ρ

    Correct Option: A

    The proportion of time the server is idle = 1 - ρ



  1. In a single server infinite population queuing model. Arrivals follow a Poisson distribution with mean λ = 4 per hour. The service times are exponential with mean service time equal to 12 minutes. The expected length of the queue will be









  1. View Hint View Answer Discuss in Forum

    λ =
    4
    , μ =
    1
    6012

    ∴ ρ =
    λ
    =
    48
    = 0.8
    μ60

    Wq = queue length =
    ρ2
    =
    (0.8)2
    = 3.2
    (1 – ρ)(1 – 0.8)

    Correct Option: B

    λ =
    4
    , μ =
    1
    6012

    ∴ ρ =
    λ
    =
    48
    = 0.8
    μ60

    Wq = queue length =
    ρ2
    =
    (0.8)2
    = 3.2
    (1 – ρ)(1 – 0.8)


  1. In a time series forecasting model, the demand for five time periods was 10,13,15,18 and 22. A linear regression fit resulted in an equation F = 6.9 + 2.9 where F is the forecast for period f. The sum of absolute deviations for the five data is









  1. View Hint View Answer Discuss in Forum

    F = 6.9 + 2.9 t
    F1 = 6.9 + 2.9 × 1 ⇒ 9.8
    F2 = 6.9 + 2.9 × 2 ⇒ 12.7
    F3 = 6.9 + 2.9 × 3 ⇒ 15.6
    F4 = 6.9 + 2.9 × 4 ⇒ 18.5
    F5 = 6.9 + 2.9 × 5 = 21.4
    D1 = 10 D2 = 13 03 = 15
    D4 = 16 D5 = 22
    SAD = ∑ |ei|
    SAD = |10 − 9.8| + |13 − 12.7| + |15 − 15.6| + |18 − 18.5| + |22 − 21.4 |
    Absolute Deviation = 2.2

    Correct Option: A

    F = 6.9 + 2.9 t
    F1 = 6.9 + 2.9 × 1 ⇒ 9.8
    F2 = 6.9 + 2.9 × 2 ⇒ 12.7
    F3 = 6.9 + 2.9 × 3 ⇒ 15.6
    F4 = 6.9 + 2.9 × 4 ⇒ 18.5
    F5 = 6.9 + 2.9 × 5 = 21.4
    D1 = 10 D2 = 13 03 = 15
    D4 = 16 D5 = 22
    SAD = ∑ |ei|
    SAD = |10 − 9.8| + |13 − 12.7| + |15 − 15.6| + |18 − 18.5| + |22 − 21.4 |
    Absolute Deviation = 2.2



  1. The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is









  1. View Hint View Answer Discuss in Forum

    Way to locate machine at four plans
    4! = 24

    Correct Option: D

    Way to locate machine at four plans
    4! = 24