Home » Aptitude » Time and Work » Question
  1. A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is
    1. 10
    2. 12
    3. 9
    4. 15
Correct Option: C

(A + B)’s 1 day’s work =
1
6

A’s 1 day’s work =
1
18

∴ B’s 1 day’s work =
1
-
1
618

=
3 - 1
=
2
=
1
18189

∴ Required time = 9 days
Aliter : Using Rule 4,
Time taken by B =
xy
days
x - y

=
6 × 18
= 9 days
18 - 6