A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is
-
- 16
- 8
- 12
- 24
Correct Option: B
(A + B)’s 1 day’s work = | 8 |
(B + C)’s 1 day’s work = | 12 |
(A + B + C)’s 1 day’s work = | 6 |
∴ C’s 1 day’s work = | - | |||
6 | 8 |
= | = | |||
24 | 24 |
A’s 1 day’s work
= | - | = | = | |||||
6 | 12 | 12 | 12 |
∴ (A + C)’s 1 day’s work
= | + | = | = | |||||
12 | 24 | 24 | 8 |
∴ Required time = 8 days
Aliter : Using Rule 5,
Let the time taken by A and C is x days
⇒ 6 = | 8x + 96 + 12x |
6 = | 20x + 96 |
120x + 576 = 192x
72x = 576