  1. A, B and C working separately can do a piece of work in 11 days, 20 days and 55 days respectively. In how many days, the work will be completed if A is assisted by B and C on alternate days ?
    1. 2
    2. 6
    3. 4
    4. 8
Correct Option: D

(A + B)’s 1 day’s work

=
1
+
1
1120

=
20 + 11
=
31
220220

(A + C)’s 1 day’s work
=
1
+
1
1155

=
5 + 1
=
6
5555

Work done in first two days
=
31
+
6
22055

=
31 + 24
=
55
=
1
2202204

∴ Required time = 2 × 4 = 8 days