A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
-
- 16 days
- 24 days
- 28 days
- 29 days
Correct Option: B
∵ A’s 1 day’s work = | 18 |
∴ A’s 12 days’ work = | = | |||
18 | 3 |
∴ Remaining work
= 1 – | = | |||
3 | 3 |
∵ Time taken by B in doing | work = 8 days | 3 |
∴ Time taken by B in doing whole work
= 3 × 8 = 24 days