  1. A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together ?
    1. 33
      8
    2. 40
      9
    3. 41
      10
    4. 42
      11
Correct Option: B

A’s 1 day’s work =
1
8

B’s 1 day’s work =
1
10

(A + B)’s 1 day’s work
=
1
+
1
=
5 + 4
=
9
8104040

∴ Required time =
40
days
9