  1. A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before completion of the work. In how many days was the work done ?
    1. 13
    2. 12
    3. 14
    4. 11
Correct Option: D

Let the work be completed in x days.
According to the question,
C worked for (x – 4) days

x
+
x
+
x - 4
= 1
243040

5x + 4x + 3(x - 4)
= 1
120

12x - 12
= 1
120

12 (x - 1)
= 1
120

x - 1
= 1 ⇒ x - 1 = 10
10

⇒ x = 10 + 1 = 11 days