A and B together can finish a work in 30 days. They worked on it for 20 days and then B left the work. The remaining work was done by A alone in 20 days more. In how many days can A alone finish the work?
-
- 48 days
- 50 days
- 54 days
- 60 days
Correct Option: D
∴ (A + B)’s 20 days’ work = | |
30 |
(A + B)’s 1 day’s work = | = | ||
30 | 3 |
Remaining work = 1 – | = | ||
3 | 3 |
Time taken by A in doing = | of work = 20 days | |
3 |
∴ Time taken by A in doing whole work = 3 × 20 = 60 days