A man, a woman and a boy can complete a job in 3, 4 and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in 1/4 of a day?
-
- 1
- 4
- 19
- 41
Correct Option: D
1 man’s 1 day’s work = | 3 |
1 woman’s 1 day’s work = | 4 |
1 boy’s 1 day’s work = | 12 |
(1 man + 1 woman)’s | day’s work | 4 |
= | ![]() | + | ![]() | = | 4 | 3 | 4 | 48 |
Remaining work
= 1 – | = | |||
48 | 48 |
Now,
1 boy’s | day’s work | 4 |
= | × | = | ||||
4 | 12 | 48 |
∴ | work will be done by | × 48 = 41 boys. | ||