  1. Three men can complete a piece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work ?
    1. 1 days
    2. 2 days
    3. 3 days
    4. 4 days
Correct Option: B

Work done in two days =
1
× 2
6

=
1
, remaining work =
2
33

M1D1
=
M2D2
W1W2

3 × 2
=
6 × D2
1
2
33

⇒ D2 =
3 × 2 × 2
= 2 days